PERT chart definition

What is a PERT Chart?

A PERT chart gives a visual representation of the critical path of a project. This critical path is the sequence of interdependent activities that will require the longest time period to complete. Each task on the chart is labeled with high and low estimated start and finish times, which can be used to determine where there is slack in the system and where to focus attention on compressing the schedule.

PERT allows for the inclusion of variable amounts of time for each task. Thus, each task has a most likely, pessimistic, and optimistic duration attached to it. The optimistic and pessimistic durations should have a probability in the 10-20% range. These three estimates are then combined to arrive at a single estimated duration for each task. The calculation of this expected task time is as follows:

[(Optimistic estimate) + (4 x Most likely estimate) + (Pessimistic estimate)] ÷ 6

In addition, the chart contains all tasks that must be addressed before a project can be completed, the sequence in which they must be completed, and the time requirements for each one. A PERT chart is especially useful for the management of more complex projects that would overwhelm a Gantt chart.

The PERT acronym is an abbreviation of the term Program Evaluation and Review Technique.

Related AccountingTools Courses

Contract Management

Project Accounting 

Project Management 

Advantages of PERT Charts

A key advantage of a PERT chart is that managers can use it to monitor the resources required to complete a project, as well as to estimate how much more time is required to complete it. Another advantage is that a PERT chart identifies exactly who is responsible for each activity in a process, so it is easy to pinpoint who needs to complete which tasks. A further advantage is that a PERT chart can be used to model a variety of different scenarios, to see how variations in the amount of resources applied will alter the outcome of a project.

Disadvantages of PERT Charts

Though PERT charts are generally useful, they have certain disadvantages that can affect their efficiency and usability. Here are the key drawbacks:

  • Complexity for large projects. PERT charts can become very intricate and difficult to manage for large projects with many tasks, dependencies, and milestones.

  • Time-consuming to create. Creating a PERT chart requires detailed planning and the estimation of time for each task. The need for accurate data and dependency mapping can make the process labor-intensive and slow.

  • Dependent on accurate estimates. PERT relies heavily on the accuracy of time estimates for tasks (optimistic, pessimistic, and most likely times). If these estimates are inaccurate, the entire chart and the resulting schedule may become unreliable.

  • Not flexible. Updating the chart to reflect changes in the project scope or schedule can be cumbersome and may require significant adjustments. The rigidity can make it less suitable for dynamic, fast-changing projects.

  • Focuses on time rather than other factors. PERT primarily emphasizes time management and critical path identification, potentially neglecting other important project aspects like resource allocation and cost management.

  • Requires specialized knowledge. Stakeholders and team members need to understand PERT charts and their interpretation, which may require training.

  • Does not include resource constraints. PERT charts do not inherently factor in resource availability, which can lead to unrealistic project timelines if resource limitations are not considered.

  • Not ideal for agile processes. PERT’s linear and deterministic nature makes it less adaptable for iterative project management methodologies like Agile, where flexibility and continuous adjustments are key.

Understanding these disadvantages can help you decide if a PERT chart is the right tool for your project or if other project management tools might be more appropriate.